If your next shutdown, turnaround or outage runs on or after 1 December 2026, it will be delivered under Australia’s new Workplace Exposure Limits (WEL). From that date, the WEL list replaces the Workplace Exposure Standards (WES) list, following implementation into the WHS laws of each jurisdiction. Until 30 November 2026, the current WES values still apply.*
Most limits aren’t changing, but some are being lowered or raised, some substances are being added, and some are being listed differently. Shutdowns bring many of the tasks that generate airborne contaminants, such as cutting, grinding, welding, spraying and running combustion engines, into one short, busy window. That makes the shutdown plan the right place to deal with the change. Here’s how to work through it, from planning to close-out.
Workplace Exposure Limits: What Hasn't Changed
The core duty for a person conducting a business or undertaking (PCBU) is the same: eliminate risks from airborne contaminants so far as is reasonably practicable, or otherwise minimise them. A WEL is a limit that must not be exceeded, but it isn’t a line that marks exposure as “safe” or “unsafe”. Workers and their health and safety representatives must still be consulted when identifying hazards and deciding on controls.
Innovative Storage? We're Up For It.
Our vertical storage hubs provides efficient, organised storage with user-friendly customisable options.
Before Mobilisation: Identify What the Scope Will Put in the Air
Work through the shutdown scope task by task, not just the purchase list. Contaminants can be generated even when no hazardous chemical was bought. Check the Safety Data Sheets for degreasers, coatings and cleaning agents, ask the crews, and record the contaminant, task, who is exposed, for how long and how often.
Then compare each contaminant against the current WES and incoming WEL using Safe Work Australia’s summary of changes or its free Hazardous Chemical Information System (HCIS). For shutdown work, pay attention to:
- Diesel-Powered Plant: Diesel particulate matter gets a new limit of 0.01 mg/m³, measured as respirable elemental carbon. Include generators, compressors, lighting towers and mobile plant in your assessment, not just the work itself.
- Concrete & Cement Work: Portland cement drops from 10 mg/m³ to 1 mg/m³, measured as respirable dust.
- Silica, Benzene & Formaldehyde: Among nine substances staying at current values from 1 December 2026.
- Skin Notations: Some substances can be absorbed through the skin. Exposure limits and respirators only deal with what’s breathed in, so build gloves and protective clothing into your PPE kitting.
Before Mobilisation: Assess Exposure for Shutdown Conditions
Exposure data needs to be current and representative of the processes, equipment and controls involved. Data gathered during normal operations may not reflect shutdown tasks, and a result that sat comfortably under an old WES may be close to, or over, a lower WEL.
- Adjust for Shutdown Rosters: Most limits are an 8-hour time-weighted average (TWA). The 10- and 12-hour rosters common in mining and construction mean more exposure and less recovery time, so the TWA may need adjusting downwards. Get a qualified professional, such as an occupational hygienist, to calculate this.
- Decide Whether Monitoring Is Needed: The WEL change doesn’t automatically require new air monitoring. It is required if you aren’t certain, on reasonable grounds, whether exposure exceeds the limit, and a lower limit may create that uncertainty. Engage a competent person during planning, not mid-shutdown.
- Plan for High Results: If results are above the limit, improve your controls, protect workers in the meantime, then check again. In NSW, notification is also required when the exposure standard for respirable crystalline silica is exceeded.
At the Workface: Control the Risk
Work through the hierarchy of controls from the top, ideally while methods, equipment and layout can still be changed in the plan. When crews clean up, wet wiping or a H-class vacuum removes settled dust, while dry sweeping or compressed air puts it back into the air.
- Elimination & Substitution: Remove the contaminant or process, or use a less hazardous material or method.
- Isolation: Separate people from the source with enclosures or restricted areas, such as around running diesel plant.
- Engineering Controls: Capture contaminants at the source with local exhaust ventilation (LEV), dust suppression, water sprays or on-tool extraction. General ventilation on its own is rarely enough for significant sources.
- Administrative Controls & PPE: Procedures, task rotation, housekeeping and access controls support higher-order controls, with respiratory protective equipment (RPE) for any remaining exposure.
At the Workface: Respiratory Protection for a Peak Workforce
Respirators reduce exposure; they don’t eliminate it. RPE protection can only be counted towards WEL compliance once all reasonably practicable higher-order controls are in place or have been evaluated, and the RPE is selected, worn and maintained correctly.
- Check the Protection Level: If a limit drops or exposure is higher than expected, you may need a higher protection level or better upstream controls.
- Fit Test Before Mobilisation: Tight-fitting respirators need a fit test by a competent tester, such as a RESP-FIT accredited tester, before first use, when a new make or model is issued and when facial changes may affect the seal. With a large contract workforce, build fit testing into onboarding rather than leaving it to day one.
- Know the New Standards: AS/NZS 1715 and AS/NZS 1716 will operate in parallel with the new AS/NZS ISO 16975 series until 2030. Ratings can’t be compared directly, so confirm a product’s classification with the manufacturer.
- Consider Loose-Fitting Options: For workers who can’t get a reliable seal, for example because of facial hair, a loose-fitting powered air-purifying respirator (PAPR) may be an option if it provides the required protection level.
Close-Out: Verify, Record and Carry It Forward
Before demobilising, confirm your controls did their job: monitoring results, extraction checks, fit tests, training and maintenance records. Air monitoring records must be kept for at least 30 years. Changes to scope, substances, equipment or rosters for the next shutdown should send you back to the start.
Your Pre-Shutdown WEL Checklist
- Scope: Have we listed every contaminant the scope will generate, including from diesel plant, with input from crews, and checked each against the WEL?
- Data: Is our exposure data representative of shutdown tasks and adjusted for roster length?
- Controls: Have we used higher-order controls before relying on PPE, and does our RPE still provide enough protection?
- Records: Are fit tests and training complete before mobilisation, and do we know what triggers a review?
How SFI Helps
SFI Australia supports major shutdowns across the mining, energy, construction and manufacturing sectors, from planning to close-out:
- Cold Cutting & Machining Solutions: Pipe cutting and bevelling equipment from specialist brands including WACHS and Orbitalum, worth considering when you review hot cutting methods.
- PPE & RPE Kitting: Respiratory protection, filters and consumables, stocked in on-site stores close to the work force. Additional Decontamination Hubs can also support major shutdowns, ensuring correct compliance.
- Digital Issue Records with Monitor: SFI’s Monitor Logistics Management System tracks issues down to the individual worker, supporting your close-out records.
- Backed by ATOM Group: As part of ATOM Group, SFI can connect you with ATOM Safety, who can visit your site, review your current safety equipment and trial suitable products with your team.
*This article is provided as a general guide only and should not be relied on as legal, safety, or occupational hygiene advice. Workplace health and safety rules vary across states and territories, and every site has its own risks. Always check the current rules with your local regulator and consult a qualified professional for your site, as SFI Australia is not liable for any loss or damage resulting from the use of this information.
Speak With Us
Since 1977, we’ve been delivering intelligent end-to-end solutions for the Australian mining, energy, construction and manufacturing sectors.
Our proud legacy has been built on consistency and innovation. We reduce downtime on sites and provide unmatched logistical efficiencies.
We take the time to listen and understand before working tirelessly to deliver successful outcomes.
When you need a partner that won’t let you down — we’re up for it.
Steve Thomas | Director & National Account Manager